Notice on the progress of key construction projects in the second quarter of 2020

According to the requirements of "Zizhou county project construction management measures" (Tzf [2020] No. 15), the progress of key construction projects in 2020 in our county in the second quarter is hereby reported as follows:

I. General Situation of the project

This year, in accordance with the general idea of "starting work in one batch at the end of March, adjusting one batch at the end of April, and planning a batch of reserves at the end of September", a total of 67 key construction projects have been arranged, with a total investment of 6.676 billion yuan and an annual planned investment of 4.311 billion yuan. Among them, there are 19 continued projects, 43 new projects and 5 reconstruction and expansion projects. Among the 67 projects, government investment accounted for 30.2% of the annual investment, private investment accounted for 18.3% of the annual investment, and private investment accounted for 51.5% of the annual investment. The proportion of social capital has reached the highest level in the past years, and the project structure has been optimized to the greatest extent.

II. Project promotion

According to the requirements of the work task account of Zizhou County in 2020 (ZBF [2020] No.6), the projects that can start on schedule and promote smoothly are marked with green; the projects with slow progress or unable to advance according to the schedule due to objective reasons are marked with yellow; and the projects with slow progress (or no progress) are marked with red.

i. By the end of June, 46 projects under construction (or completed) have been started

1. Three completed projects (marked as green) have been completed, namely, the greening of Zizhou County crossing line of Suiyan expressway, the greening and beautification of County town, and the construction of ten thousand mu mountain Apple poverty alleviation demonstration base.

2. 29 projects under construction and progressing smoothly (marked as green), including the construction of teaching building and apartment building of Mata left behind children's school, national e-commerce into rural Demonstration County, Sihao rural road Mending Project, comprehensive archives construction project, ecological environment management project, provincial forest city garden city civilized city construction project, Astragalus membranaceus comprehensive development and traditional Chinese medicine Material extract production line project, county shantytown reconstruction project, cattle and sheep slaughtering, processing and refrigeration integration construction project, road hardening project of Northern Yuan forest farm, treatment project of major potential safety hazards of rural roads, sewage treatment station construction project of Matigou Town, mountain Apple construction project of the whole county, national entrepreneurship construction project, sewage treatment station and supporting sewage pipe network construction project of laojundian town Objectives: the shantytown reconstruction project of yidaojie in Matigou small town, Rural Revitalization demonstration village construction project, precision poverty alleviation project, animal husbandry industrialization construction project, sewage treatment plant expansion project, human settlement environment improvement project, public library construction project, yingma'an Sino German poverty alleviation industrial park construction project, government service center construction project, conversion of farmland to forest and walnut industry construction project The second phase expansion project of Yongxing coal mine, the construction project of superfine cashmere goat breeding demonstration base, the construction project of traditional Chinese medicine base and the construction project of Macha Astragalus base.

3. 14 projects under construction (marked in yellow) are under construction, including Zhangzhai area land reserve project, urban three work in one project, municipal engineering of Zimi road in hejiagou planning road, flood drainage tunnel construction project, municipal engineering of jing16 road and 17 road and 18 road, cultural center exhibition project, 110kV Fengqu substation construction project, Dali Road sewage pipe jacking project, and middle school The project includes the integration of medicinal materials construction project, photovoltaic agricultural vegetable greenhouse base construction project, old community reconstruction project, county sewage main pipe relocation project, court construction project and water purification plant expansion project.

ii. 21 projects not started

1. Among them, 9 new projects (marked in yellow) are the construction of Matigou Industrial Park, the construction of construction waste treatment plant, the relocation of administrative examination and approval service hall, the construction of Miaojiaping facility fruit and vegetable experimental demonstration base, the construction of high standard farmland, the construction of Dali road demonstration Street, and the big data of emergency management smart city Platform project, neighborhood center construction project and reconstruction project of Miaojiaping old street.

2. Five slow projects (marked in yellow) were promoted, including road upgrading project, tongcun Tongzu highway construction project, warping dam maintenance and reinforcement project, outpatient building reconstruction project of people's Hospital, construction project of Huaining Bay expressway connecting line

3. There are 7 slow-moving projects (marked in red), including fruit production and marketing service center construction project, geological disaster control project, CDC construction project, maternal and child health station construction project, jing14 Road municipal road construction project, slope farmland soil erosion comprehensive treatment project and ecological comprehensive control demonstration project.

III. Existing problems

i. Slow (or slow) propulsion

1. There are 7 projects that are slow to advance due to difficulties in land acquisition or demolition, including municipal engineering of Jimi road in hejiagou planning road, municipal engineering of jing16 road passing through 17 road and 18 road, flood discharge tunnel construction project, sewage pipe jacking project of Dali Road, construction project of Dali road demonstration Street, land reserve project of Zhangzhai area and reconstruction and expansion project of water purification plant.

2. There are 3 projects that can not be started on time due to the slow advance of the preliminary work, including the construction project of CDC, the construction project of MCH station and the construction project of Huaining Bay high-speed connecting line.

3. One project with slow progress due to large funding gap, namely the reconstruction project of Miaojiaping old street.

4. Due to the need for land adjustment and planning, there are three slow projects, namely, the construction of photovoltaic agricultural vegetable greenhouse base, the construction of construction waste treatment plant, and the follow-up assistance to the construction of Matigou Industrial Park.

5. There is one project that can not be started on schedule due to the lack of funds from provinces and cities, that is, the comprehensive control project of soil and water loss on slope farmland.

6. For other reasons, the construction project of 110kV Fengqu substation was slow due to serious obstruction and drainage problems, and the cooperation with Beijing scientific research institutions was slow due to the impact of epidemic situation on the integrated construction project of traditional Chinese medicine.

ii. Lagging behind in China's entry into WTO

At present, there are 23 key construction projects under construction, but they have not yet been incorporated into the system, namely, the four good rural highway short board project, the ecological environment treatment project, the cattle and sheep slaughtering, processing and refrigeration integration construction project, the treatment project of major potential safety hazards of rural roads, the county's mountain Apple construction project, the national entrepreneurship construction project, the reconstruction and expansion project of sewage treatment plant, and the demonstration of superfine cashmere goat breeding Fan base construction project, traditional Chinese medicine base construction project, Macha Astragalus base construction project, Zhangzhai area land reserve project, urban three work in one project, hejiagou planning road ZIMI Road Municipal Engineering, flood drainage tunnel construction project, jing16 road through 17 road through 18 Road Municipal Engineering, 110kV Fengqu substation construction project, Dali Road sewage pipe jacking project, Chinese herbal medicine integration Construction project, photovoltaic agricultural vegetable greenhouse base construction project, old community reconstruction project, county sewage main pipe relocation project, court construction project and water purification plant expansion project.

IV. Suggestions for the next step

i. Accelerate the preliminary work of the project. If the project is slow to advance, the competent unit should pay close attention to the task target, arrange the construction period in reverse, carefully dissect the root cause of the problem, decompose and implement the responsibilities at all levels, and strengthen the work measures to ensure the smooth progress of the project.

ii. Strive for funds up. If there is a gap in funds, the promotion departments should pay close attention to the policy trends of provinces and cities in China, accurately plan the projects that meet the support, actively communicate with the relevant departments at higher levels, and increase the efforts to strive for funds.

iii. Make sure that it is unified. All departments should attach great importance to the unified work of fixed investment, assign special personnel to take charge of it, timely connect with the Statistics Bureau, carefully sort out the projects under construction but not included in the unified system, and complete the warehousing and unified declaration of the projects under construction as soon as possible.